Arnold Hill primary school ran one of the few remaining school coal-fired boiler plants. This offered a unique challenge in ensuring a new gas supply and installation of a below-ground gas main. This was done in time for their replacement boiler plant by the summer shutdown of 2018. We worked closely with the school at the early stages to ensure design work was completed to allow application for a new meter. Whilst we commenced with the removal of the large coal-fired plant and associated equipment, groundwork was underway to allow the installation of a new gas distribution through the schools grounds. Close coordination was needed to ensure minimal impact on the schools partners who continued to operate throughout our time on-site. The project was delivered on-time and within budget.