ASTON UNIVERSITY

SU/BIAD - Demolition Enabling Work

The area of the new cold-water storage tank is temperature controlled with local operated and installed Split air conditioning units.

The newly formed tank room and the storage/ electrical room are completed with all new containment, power supply, local distribution board, small power, lighting, lighting control and fire alarm.

A new BMS control panel for the new main water tank and booster set linked to the University main facilities system, via a newly installed data network cable.

Four number external ducts have been laid below ground from the EBRI building to the new feeder pillar located in Car Park 5.

Using the new duct route a main power supply has been installed from EBRI to a new feeder pillar in car park 5.